The fight to protect Hurummarka
Plans for a possible explosives plant in Hurummarka are under consideration. The matter has not been decided – and can still be influenced.
Updated November 2026
📍 In brief
2024: Assessment begins + 15-year contract with Northrop Grumman
2025: Hurummarka identified as the preferred site
Sept 2025: 5,000 signatures + demonstration
Dec 2025: Parliament allocates NOK 235 million for phase two
Jan 2026: The state takes over the planning process
Feb 2026: Protection proposal + the Citizens’ Campaign is founded
7 May 2026: Protection proposals voted down in Parliament
13 May 2026: Design contracts awarded mid-hearing
12 June 2026: Citizen proposals to municipality and county
15 June 2026: 1,189 hearing submissions, 725 of them using the Citizens’ Campaign’s template
June–Sept 2026: Fieldwork and ground investigations before the planning programme is finalised
10 Sept 2026: Municipal council rejects call for alternatives
Oct 2026: Government proposes up to NOK 309 million for Chemring Nobel in 2027
31 Oct 2026: Up to 1,000 people demonstrate in Oslo
Winter 2026–27: New public hearing on the zoning proposal
👉 The matter is still open – the planning process has not been decided
🏭 Assessment process begins
The Norwegian government begins assessing the need for, and possible locations of, a new explosives plant in collaboration with Chemring Nobel.
📝 May – Chemring Nobel signs 15-year contract with Northrop Grumman
Chemring Nobel enters into a 15-year supply agreement with the American defence manufacturer Northrop Grumman for the explosive HMX, with an initial order worth 83 million dollars. Deliveries begin in 2026 – the same year the planning process for the new plant is still ongoing.
📍 Hurummarka identified as the preferred site
Hurummarka is singled out as the most likely location in the process.
💬 Local engagement grows
Local engagement increases, with growing questions about the process, its consequences, and the knowledge base behind it.
✍️ Petition launched
A petition against the plans is launched, gathering around 5,000 signatures.
📬 3 September – Handover to Parliament
The signatures are handed over to the Norwegian Parliament (Stortinget).
🚩 Demonstration at Eidsvolls plass
On the same day, a large demonstration is held outside Parliament, making the opposition to the plans visible.
💰 December – Parliament allocates NOK 235 million
Parliament adopts a proposition from the Ministry of Defence allocating 235 million kroner to Chemring Nobel for phase two of the project – before the planning programme has been finalised and before the public hearing has taken place.
🏛️ January – State-led zoning
The state takes over the planning process through state-led zoning (statlig regulering).
🌿 February – Protection proposal
The Green Party (MDG), Red Party (Rødt) and Socialist Left Party (SV) put forward a parliamentary proposal to protect Hurummarka under the Marka Act (markaloven). The proposal asks the government to formally include Hurummarka in the Act and to carry out a new feasibility study in which travel time is not used as a weighted variable.
🤝 23 February – The Citizens’ Campaign is founded
The Citizens’ Campaign for Hurummarka (Folkeaksjonen for Hurummarka) is established. The organisation begins coordinated work on information sharing and mobilisation.
📣 Further mobilisation
Information meetings, hikes and activities are organised to engage more people.
🏕️ April – Activists occupy a house in Hurummarka
The group Knus Krigsmaskinen («Crush the War Machine») occupies an abandoned house in Avgrunnsdalen, in the middle of the planned factory site, in protest against the plans. The action receives national media coverage.
📄 27 April – Planning programme out for public hearing
The planning programme is published for public consultation by the Norwegian Defence Estates Agency (Forsvarsbygg), with a deadline of 15 June. This phase determines what will be assessed going forward.
🚶♀️ 3 May – Open hike in Hurummarka
An open event to get to know the area and the case.
🗳️ 5 May – Parliamentary debate
Parliament debates the proposals concerning Hurummarka. The vote is postponed to Thursday 7 May.
🗳️ 7 May – Protection proposals voted down
All proposals are voted down – both inclusion in the Marka Act and the demand for a new feasibility study. The proposal that came closest (from the Centre Party and Red Party, calling for a new feasibility study in parallel with the process) received 20 votes. The fight continues in the hearing process. Read more (in Norwegian).
🏫 11 and 19 May – Forsvarsbygg’s information meetings
Forsvarsbygg holds open information meetings at Tofte schools, as well as open office days. Many residents raise critical questions about the process and the lack of assessment of alternatives.
📺 12 May – Criticism of the media coverage
The campaign publishes an analysis of how Chemring is allowed to set the premises in NRK’s coverage of the case. Read more (in Norwegian).
⚠️ 13 May – Design contracts awarded mid-hearing
Chemring Nobel announces that Aibel and Multiconsult have been selected as partners to develop concrete solutions for the plant – while the public hearing is still ongoing, and before the planning programme has been finalised.
📣 June – The case gains national attention
Magnus Støre publicly speaks out against the plans in VG, and Sigrid Bonde Tusvik writes about Hurummarka and the Oslofjord in Dagsavisen. More and more voices are joining the opposition.
🗳️ 12 June – Citizen proposals to municipality and county
Two citizen proposals (innbyggerforslag) to protect Hurummarka are launched on minsak.no – one to Asker municipal council and one to Akershus County Council. With enough signatures, politicians are required to consider the proposals. Both proposals reached their targets. See how it went (in Norwegian).
✅ 15 June – 1,189 hearing submissions
The deadline for the planning programme hearing passes. 1,189 submissions came in from individuals, organisations and affected parties across Norway and abroad. 725 of them were sent using the Citizens’ Campaign’s template – a historic mobilisation for Hurummarka. See the templates and arguments.
🔎 June – Fieldwork at Tofte before the planning programme is finalised
Landowners and neighbours receive letters saying that Norconsult, on behalf of Forsvarsbygg, will carry out fieldwork at Tofte from June to September. The surveys are to be used in the impact assessment, but the planning programme that sets the framework for that assessment has not been finalised. The Citizens’ Campaign asks the Ministry of Local Government and Regional Development (KDD) for clarification. Read more (in Norwegian).
⚖️ 7 July – Complaint to the Parliamentary Ombud
The Citizens’ Campaign complains to the Parliamentary Ombud (Sivilombudet) that the case was made a state zoning plan. KDD has confirmed that there is no formal decision on this beyond the press release from January. In September the Ombud replies that the complaint must wait until the state has adopted the plan, if it does. We can then complain again, and the Ombud will consider whether to look into the case more closely, including the decision to make it a state plan.
📨 6 August – KDD replies about the fieldwork
KDD replies to our letter about the fieldwork itself, as we asked. The ministry writes that the fieldwork will not be used as an argument for keeping Tofte as the only alternative, and that which alternatives will be assessed is decided only when the planning programme is finalised. The ministry does not respond to our request that data and reports from the fieldwork be published as the work goes on.
👥 25 August – The Citizens’ Campaign’s first annual meeting
The annual meeting elects a new board and adopts a plan for the work ahead, including a leaflet, a public meeting and a large demonstration in Oslo. Meet the board.
🪨 4 September – Chemring Nobel announces ground investigations
Chemring Nobel announces that it will start ground investigations in the plan area at Tofte. Multiconsult will survey rock and loose deposits with a tracked drilling rig for about a month. The company calls these preliminary investigations, but they too take place before the planning programme has been finalised. Read the RHA article (in Norwegian).
🏛️ 10 September – Municipal council rejects call for alternatives
Asker municipal council considers the municipality’s consultation response and the citizen proposal ‘Bevar Hurummarka’ (Preserve Hurummarka). A proposal to require that at least one alternative outside Hurummarka be assessed as a full alternative is defeated by 43 votes to 11. The citizen proposal is referred to the hearing case.
💰 October – Up to NOK 309 million proposed for Chemring Nobel
In its draft state budget for 2027, the government proposes up to NOK 309 million for Chemring Nobel. Around NOK 150 million of this is meant to speed up the new plant, so that an investment decision can be made in mid-2027. Parliament adopts the budget in December. No final decisions have yet been made about the factory in Hurummarka.
🚩 31 October – Up to 1,000 people demonstrate in Oslo
Up to 1,000 people gather outside the Government Quarter (Regjeringskvartalet) for Hurummarka. After the speeches, the march goes down Karl Johans gate, past Parliament, to Universitetsplassen. 31 organisations are behind the demonstration. See the photos (in Norwegian).
🎵 November – New recruitment video
Thea Glenton Raknes has written the protest song «Om vi lar oss blende» for Hurummarka. The Citizens’ Campaign launches a recruitment video with the song, footage from the forest and from the demonstration in Oslo. Watch the video (in Norwegian).
⚠️ STATUS
The planning programme has not been finalised yet. The next step is a public hearing on the zoning proposal with an impact assessment, which Forsvarsbygg expects in winter 2026–27. Everyone can submit input again then.
The state plans to adopt the zoning plan during 2027. The matter has not been decided.
Find out how you can help save Hurummarka: