Why This Matters

Citing the security situation after Russia’s invasion of Ukraine, the Norwegian government is pressing ahead with a new explosives facility over local objections and environmental concerns. Yet the state’s own planning programme sets 2030 as the date by which the plant should be ready — and campaigners question whether the urgency driving the case is real.

The facility is planned for Chemring Nobel, the Norwegian explosives manufacturer that already operates a plant at Sætre, on the same Hurum peninsula. The chosen site, Hurummarka, is a continuous, much-used forest landscape beside the Oslofjord. The Citizens’ Campaign for Hurummarka (Folkeaksjonen for Hurummarka) is not opposed to Norway having a defence capability. It objects that Hurummarka was chosen without alternatives being properly assessed, and that a long-term industrial decision, still years from producing anything, is being justified by short-term wartime urgency — at the expense of the fjord, the forest, and due process.

The proposed site lies close to the Oslofjord, one of the region’s most ecologically stressed waters — already in documented decline and the subject of a national rescue plan. The campaign raises concerns about discharge into the fjord, and points to EU water rules, including the principle established in the EU Court of Justice’s Weser ruling, which apply to Norway through the EEA agreement and prohibit measures that worsen the status of a body of water.

The decision is being made through a state-led zoning process (statlig reguleringsplan) that moves authority to national ministries and sets aside the objection and appeal rights communities would normally hold. For many that raises a broader question: how should a democracy decide where security-critical infrastructure is built, and who gets a say?

For an international audience, the story sits where three threads meet:

  • A defence build-up set against environmental law — and whether the case for urgency holds
  • The future of the Oslofjord and the reach of EU / EEA water law
  • How a democracy decides where security-critical infrastructure goes, and who gets a say

Press Contact

International & English-language press
Victor Ljunggren Szepessy, board coordinator
Email: vicszepessy@gmail.com
Phone: +47 940 68 710

Norwegian press & general enquiries
Isak Gregers Eriksen, spokesperson
Phone: +47 989 96 921
Email: hurummarka@gmail.com

We are available for interviews and can provide background documentation, expert contacts and local perspectives.

About the Citizens’ Campaign for Hurummarka

The Citizens’ Campaign for Hurummarka (Folkeaksjonen for Hurummarka) is a politically independent civic initiative working to preserve Hurummarka as a continuous forest landscape and to ensure a transparent and thorough assessment of the proposed explosives facility planned for the area.

The organisation consists of local residents and professionals from a range of political and professional backgrounds, united around one issue: responsible land-use planning and long-term environmental stewardship.

Background to the Case

The Norwegian government has initiated a state-led planning process (“statlig regulering”) for the possible establishment of a new Chemring Nobel explosives production facility in Hurummarka.

The proposal raises questions regarding:

  • Location of heavy defence-related industry
  • Long-term environmental impact, including discharge to the Oslofjord
  • Democratic process and local participation
  • Consideration of alternative sites

Defence preparedness is broadly supported across the political spectrum in Norway. The question is not whether to strengthen defence, but whether this location, this timeline and this process are the right way to do it.

Key Facts

  • The proposed facility would require security fencing, restricted access and safety zones.
  • Industrial development would fragment a continuous forest area used for recreation and valued for biodiversity.
  • The state’s planning programme sets 2030 as the date by which the facility should be ready.
  • The campaign raises concerns about discharge from the site into the Oslofjord, a water body already in documented ecological decline.
  • Chemring Nobel already operates an explosives facility at Sætre, on the same peninsula.
  • Several political parties and youth organisations have publicly expressed opposition to this location and/or proposed formal protection of the area.

The campaign is not opposed to Norway having a defence capability. It opposes the choice of Hurummarka without a proper assessment of alternatives. Its concern is the location, the environmental risk and the democratic process.

Political Context

Opposition to locating the facility in Hurummarka has been expressed by several political actors, including:

  • The Green Party (MDG)
  • The Red Party (Rødt)
  • Socialist Left Party (SV)
  • Centre Party (Sp)
  • AUF Akershus (the regional youth organisation of the Labour Party)

The issue has therefore generated debate across party lines and generations.